The CER expects that companies identify and mitigate risks before they begin a project. When a risk is identified during the review of an application, the Commission of the Canada Energy Regulator (the Commission) may impose project-specific conditions to reduce risks, prevent harm, promote safety, and protect the environment.
If a project is approved, the CER will oversee the construction and operation of the project through a variety of post-approval matters, that inform safety and environmental oversight. Condition compliance and related documents were received by the CER for 51 different projects in 2021–22. When any of the filings received require a regulatory decision, the matter is brought to the Commission for decision.
The table below outlines the projects for which many post-approval filings were received. Many projects are not listed for brevity purposes.
Company and Project Name |
Number of |
---|---|
Trans Mountain Expansion Project |
534 |
NOVA Gas Transmission Ltd. – 2021 System Expansion Project |
318 |
Westcoast Energy Inc. – T-South Expansion and Reliability Project |
237 |
Westcoast Energy Inc. – Spruce Ridge Program |
148 |
NOVA Gas Transmission Ltd. – North Corridor Expansion Project |
134 |
EnCana Corporation – Leave to Abandon Deep Panuke Pipeline |
80 |
Enbridge Inc. – Line 3 Replacement Program |
75 |
NOVA Gas Transmission Ltd. – Edson Mainline Expansion Project |
71 |
ITC Lake Erie Connector LLC – Lake Erie Connector Project |
47 |
NOVA Gas Transmission Ltd. – North Montney Project |
35 |
NOVA Gas Transmission Ltd. – Approval to Abandon Meter Stations and Lateral Pipelines on the NGTL System |
32 |
NOVA Gas Transmission Ltd. – 2017 System Expansion |
24 |
Westcoast Energy Inc. – Wyndwood Pipeline Expansion Project |
13 |
TransCanada Keystone Pipeline GP Ltd. – Keystone XL Pipeline |
13 |
Trans Mountain – Edmonton Terminal Expansion Project |
12 |
Manitoba Hydro – Manitoba Minnesota Transmission Project |
10 |
NOVA Gas Transmission Ltd. – Peace River Mainline Abandonment |
7 |
Trans Mountain – Coquihalla Crossing No. 15 and 16 Replacement Project |
7 |
NOVA Gas Transmission Ltd. – Northwest Mainline Loop (Boundary Lake North Section) |
7 |
Trans Québec & Maritimes Pipeline Inc – TQM Reinforcement and Asset Purchase |
6 |
Trans Mountain – Sumas River Crossing Replacement Project |
6 |
NOVA Gas Transmission Ltd. – Exemption Order for the NPS 16 Marten Hills Producer Tie In Rehabilitation Project |
6 |
Milk River Pipeline Ltd. – Transfer of Ownership of the Milk River Pipeline System from Plains Midstream Canada ULC to Milk River Pipeline Ltd. |
4 |
NOVA Gas Transmission Ltd. – Sundre Crossover |
4 |
ExxonMobil Canada Ltd. – Goldboro Gas Plant and 26” Gathering Pipeline Abandonment |
4 |
Vantage Pipeline Canada ULC – Vantage Pipeline Project |
3 |
Foothills Pipe Lines (South BC) Ltd. – Foothills Zone 8 West Path Delivery 2023 Project |
3 |
Trans Mountain – Edmonton Terminal Facility Piping Relocations |
3 |
Trans Mountain – Burnaby Terminal Facility Piping Relocations |
3 |
NOVA Gas Transmission Ltd. – Saddle Lake Lateral Loop (Cold Lake Section) Project |
3 |
NOVA Gas Transmission Ltd. – Integration Asset Transfer |
3 |
Westcoast Energy Inc. – Silverstar Project |
2 |
NOVA Gas Transmission Ltd. – NPS 16 Mildred Lake North Lateral Relocation |
2 |
Many Islands Pipe Line (Canada) Limited – Pierceland Supply Project |
2 |
Grand Total |
1858 |