ARCHIVED - Letter to Plains Midstream Canada ULC

This page has been archived on the Web

Information identified as archived is provided for reference, research or recordkeeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

Letter to Plains Midstream Canada ULC [PDF 208 KB]

File OF-Surv-OpAud-P102-2009-2010 02
4 November 2011

Mr. David Duckett
President
Plains Midstream Canada ULC
Suite 1400, 607 8th Avenue S.W.
Calgary, AB T2P 0A7
Facsimile 403-233-0399

Dear Mr. Duckett:

Plains Midstream Canada ULC (Plains)
Board Order SO-P384-004-2011
Approval of Third Party Independent Pipeline Integrity Expert and
Fitness-for-Service Milestones and Deliverables Schedule

In response to Plains’ letter dated 28 October 2011, the Board approves Plains’ proposal to contract Robert (Bob) Coote as a third-party independent pipeline integrity expert to review the Fitness-for-Service (FFS) assessment as required by condition 5 of Board Order SO-P384-004-2011 (Order).

The Board has reviewed Plains’ proposed “Fitness-for-Service Milestones and Deliverables Schedule” as revised in Plains’ filing dated 28 October 2011 and finds that the milestones and deliverables are consistent with the requirements of the Order. However, the Board has made certain changes to the proposed schedule. The first change is to meet “with the NEB” rather than “with S.15 [Section 15 of the National Energy Board Act] Board Member” under items 5, 8, 9, 10, 12 and 14. The Board notes that either Board Member Vergette or Board staff will meet with Plains.

The second revision is to remove specific dates for items 3, 4 and 7 when Board approval was requested by Plains.

The last revision provides some flexibility to the dates for items 5, 8, 9, 10, 12, 14, and 16. The date, time and location for these items can be determined informally approximately one week prior to the actual meeting or presentation.

In compliance with condition 6 of Board Order SO-P384-004-2011, the Board approves the revised schedule as attached.

If you have any questions, please contact Joshwa Minhas, Engineer – Integrity Management at 403-299-3674 or Nadia McCarthy, Engineer – Integrity Management at 403-221-3008.

Yours truly,

Anne-Marie Erickson
Secretary of the Board

Attachment


Attachment to Board Letter
Dated 4 November 2011

Fitness-for-Service Milestones and Deliverables Schedule

  1. Further submission[1] of third party independent pipeline integrity expert to the Board - 28 October 2011
  2. Revised submission1 of FFS milestones and deliverables schedule to the Board - 28 October 2011
  3. Board approval of third party independent pipeline integrity expert
  4. Board approval of FFS milestones and deliverables schedule
  5. Meeting with the NEB and Plains Senior Management – beginning of November 2011
  6. Submission of FFS Terms of Reference to the Board – 15 November 2011
  7. Board approval of FFS Terms of Reference
  8. Progress meeting with the NEB and Plains Senior Management – mid-December 2011
  9. Progress meeting with the NEB and Plains Senior Management – mid-January 2012
  10. Progress meeting with the NEB and Plains Senior Management – mid-February 2012
  11. Completion of FFS Assessment – 29 February 2012
  12. Progress meeting with the NEB and Plains Senior Management – mid-March 2012
  13. Completion of third-party review of FFS Assessment – 31 March 2012
  14. Progress meeting with the NEB and Plains Senior Management – beginning of April 2012
  15. Submission of FFS assessment and third party expert report – 15 April 2012
  16. Presentation of Final report findings – beginning of May 2012

[1] Original submission dated 21 October 2011