Resume Work Notice – TransCanada Pipelines Limited – Order GC-001-2016
Resume Work Notice – TransCanada Pipelines Limited – Order GC-001-2016 [PDF 1123 KB]
RESUME WORK NOTICE
IN THE MATTER OF THE NATIONAL ENERGY BOARD ACT,
FOLLOWING AN ORDER UNDER SECTION 51.1
The undersigned National Energy Board Inspection Officer hereby notifies
TransCanada Pipelines Limited (TCPL)
that the hazardous or detrimental situation described in Order No. GC-001-2016 has been remedied to the satisfaction of the Inspection Officer.
Therefore,
- X Suspended work may resume, and/or
- X the measures specified in the order have been satisfied.
Dated: 23 November 2016
Inspection Officer | 1950 | ||
---|---|---|---|
Name | IO Designation # | Telephone | |
23 November 2016 | Signature |
||
Date | |||
210-517 10 Ave SW, Calgary AB T2R 0A8 |
Revised June 2016
Document #: 282393
Document #: 282393
Activity or Incident #: CVA 1617-271
- Date modified: