2014-AMP-001 [PDF]

2014-05-23

Nova Gas Transmission Ltd. Musreau Lake West Receipt Meter Station (AB) 31(a) of the Act – Construction of a pipeline without a certificate (Type B) $16,000

2014-AMP-002

2014-11-20

Canadian Natural Resources Ltd. Ladyfern Pipeline 25 of the OPR – Failure to perform pressure testing as prescribed (Type B) $28,000

2014-AMP-003 [PDF]

2014-07-02

Trans Mountain Pipeline ULC Nipisi Facility Piping at the Trans Mountain Edmonton Terminal (AB) 2(3) of the AMP – Non-compliance with Condition 2 of Order XO-T260-009-2013 $16,000

2014-AMP-004 [PDF]

2014-12-11

Dr Four Beat Energy Corporation Meter station and piping between NW5-1-11W4 and SW-1-11WA near Aden (AB) 2(2) of the AMP – Non-compliance with Conditions 3 and 4 of Order SG-D081-01-2013 $100,000

2014-AMP-005 [PDF]

2014-09-08

Steve Minotakis (Dr Four Beat Energy Corporation) Meter station and piping between NW5-1-11W4 and SW-1-11WA near Aden (AB) 2(2) of the AMP – Non-compliance with Conditions 3 and 4 of Order SG-D081-01-2013 $25,000

2014-AMP-006 [PDF]

2014-12-15

Lone Pine Resources Canada Ltd. Ojay Pipeline 2(3) of the AMP – Non-compliance with Condition 15 of Order XG-C357-09-2010 $28,000

2015-AMP-001

2015-01-22

Westcoast Energy Inc. (Spectra Energy Transmission) Dawson Creek Gas Plant (BC) 4(1) of the PPR – Failure to ensure that the company’s processing plant is designed, constructed, operated or abandoned as prescribed (Type B) $88,000

2015-AMP-002

2015-02-06

Enbridge Pipelines Inc. Edmonton to Hardisty Pipeline Project (AB) 2(3) of the AMP – Failure to comply with Condition 2 of Order XO-E101-006-2014 $16,000

2015-AMP-003

2015-02-12

Plains Midstream Canada ULC (Plains) Canada 53(1) and 55 of the OPR – Failure to conduct inspections and audits as prescribed (Type B) and Failure to document the audit as prescribed (Type B) $76,000

2015-AMP-004

2016-02-05

Enbridge Pipelines Inc. Replacement pipeline between the Cromer Terminal and the tie-in point within NW-9-926 WPM Failure to comply with Condition 2 of Order XO-E101-016-2013 Rescinded

2015-AMP-005

2016-03-10

Enbridge Pipelines Inc. Line 3 replacement project construction site, Cromer (MB) 2(3) of the AMP – Failure to comply with Condition 3 of Order XO-E101-016-2013 $76,000

2015-AMP-006

2016-02-12

Enbridge Pipelines Inc. Plains Wascana Tank 80 (SK) Failure to comply with Condition 2 of Order XO-E101-021-2013 Rescinded

2015-AMP-007

2016-02-12

Enbridge Pipelines Inc. Edmonton to Hardisty Pipeline Project (AB) Failure to comply with Condition 2 of Order XO-E101-006-2014 Rescinded

2015-AMP-008

2015-04-17

Westcoast Energy Inc. (Spectra Energy Transmission) Pine River Gas Plant (BC) 49(1.1) of the PPR – Failure to notify as Prescribed (Type A) $6,300

2015-AMP-009

2016-03-02

Westcoast Energy Inc. (Spectra Energy Transmission) Transmission North Expansion Project (BC) 2(3) of the AMP – Failure to comply with Condition 7 of Order XG-W102-005-2011 $4,000

2015-AMP-010

2016-03-02

Enbridge Pipelines Inc. Line 4, Strome (AB) 4 of the OPR – Failure to ensure that a pipeline is designed, constructed, operated or abandoned as prescribed (Type B) $28,000

2015-AMP-011

2015-07-29

Melcor Developments Ltd. Rosenthal Blvd and 224 Street, Edmonton (AB) 112(1) of the Act – Construction of a facility or excavation without leave (Type B) $28,000

2015-AMP-012

2015-12-02

Conoco Phillips Canada Operations Ltd. Elmworth Station U to B Pipeline Integrity Project, Beavertail Creek (AB) 30(1) of the Act – Operation of a pipeline without a certificate and leave to open (Type B) $28,000

2017-AMP-001

2017-12-07

Landstar Projects Surrey (BC) 6(b) of the PCR, Part I for an unauthorized activity without written permission from the pipeline company prior to excavation $28,000

 