2021–22 Annual Report of the Commission of the Canada Energy Regulator – Appendix C: Time Limits

2021–22 Time Limits

The following table shows applications which were subject to time limits for processing as per the Canadian Energy Regulator Act (CER Act). All 16 CER Act section 214 application legislated time limits were met in 2021–22.

Percentage of Decisions – Grouped by Days Remaining on Time Limits

Percentage of Decisions – Grouped by Days Remaining on Time Limits

Graphic description

Percentage of Decisions – Grouped by Days Remaining on Time Limits

Percentage of Decisions Grouped by Days Remaining on Time Limits
Time Limit Exceeded < 50 days Remaining
on Time Limit
50 – 100 days Remaining
on Time Limit
100 + days Remaining
on Time Limit
0% 6% 19% 75%

Under the CER Act, the Lead Commissioner must set a time limit for certain types of applications. The time limit must not exceed the maximum number of days indicated in the CER Act. The Commission must complete its assessment and make its recommendation or decision within this time limit. The standard time limits set by the Lead Commissioner can be found on the CER website.

Applications processed by the CER subject to time limits:

Applications processed by the CER subject to time limits

Legislation

Application Type

Time Limit

Application

Days from Completeness to Decision Issued

Decision

Date of Decision (YYYY-MM-DD)

CER Act s.214

Small Pipeline Infrastructure – Category C

300 days from application complete

NOVA Gas Transmission Ltd. – NGTL West Path Delivery 2022 Project

252

Filing C12756

2021-04-27

CER Act s.214

Small Pipeline Infrastructure – Category C

300 days from application complete

Trans Mountain Pipeline ULC – application to construct and operate – Sumas River Crossing Replacement Project

64

Filing C13003

2021-05-07

CER Act s.214

Small Pipeline Infrastructure – Category C

300 days from application complete

NOVA Gas Transmission Ltd.- application to construct and operate the Groundbirch Mainline Loop (Saturn Section) and Saddle Hills Compressor Station C4 Unit Addition

113

Filing C13065

2021-05-12

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

Alliance Pipeline Ltd – Bigstone HDD Pipe Replacement Project

30

Filing C13142

2021-05-14

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

NOVA Gas Transmission Ltd. -application to construct and operate – North Central Corridor Remediation Project

124

Filing C13467

2021-06-01

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

Westcoast Energy Inc. application regarding CS-06A and CS-07 Station Piping Replacement

60

Filing C16043

2021-11-08

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

Trans-Northern Pipelines Inc. – application to construct and operate – TNPI Dorval Tunnel Relocation Project

71

Filing C16169

2021-11-17

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

NOVA Gas Transmission Ltd. – application to construct and operate – Chambers Creek Receipt Meter Station

64

Filing C16304

2021-11-23

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

NOVA Gas Transmission Ltd. -application to install new cooling systems at the existing Hidden Lake and Hidden Lake North Compressor Stations

76

Filing C16718

2021-12-08

CER Act s.214

Small Pipeline Infrastructure – Category C

300 days from application complete

NOVA Gas Transmission Ltd. – application for the Pioneer South Pipeline Acquisition- continued operation of the Project

63

Filing C16961

2021-12-17

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

NOVA Gas Transmission Ltd. – application to construct and operate – Emerson Creek Compressor Station

124

Filing C16958

2021-12-21

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

NOVA Gas Transmission Ltd. – application to construct and operate – Smoky River South Sales Meter Station

50

Filing C16997

2021-12-22

CER Act s.214

Small Pipeline Infrastructure – Category B

210 days from application complete

NOVA Gas Transmission Ltd. – application to construct and operate – McLeod River Sales Meter Station

59

Filing C17440

2022-01-21

CER Act s.214

Small Pipeline Infrastructure – Category C

300 days from application complete

Foothills Pipe Lines (South B.C.) Ltd. – Foothills Zone 8 West Path Delivery 2023 Project

250

Filing C17973

2022-02-07

CER Act s.214

Small Pipeline Infrastructure – Category C

300 days from application complete

Enbridge Pipelines Inc. (on behalf of Westover Express Pipeline Ltd.) application for Mechanical and physical separation of Line 10 from the existing Enbridge assets to allow Westover Express Pipeline Ltd.

73

Filing C17953

2022-02-28

CER Act s.214

Small Pipeline Infrastructure – Category C

300 days from application complete

Westcoast Energy Inc. – application to construct and operate – Grizzly Valley Mainline Crossing Project

111

Filing C18336

2022-03-23