ARCHIVED – Emera Brunswick Pipeline Company Ltd. - Detailed Route - MH-3-2007 and MH-1-2008

This page has been archived on the Web

Information identified as archived is provided for reference, research or recordkeeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

Introduction

The National Energy Board held a public hearing on 28 January 2008 in response to oppositions about portions of the proposed detailed route of the Emera Brunswick Pipeline to be constructed by Emera Brunswick Pipeline Company Ltd.

Objections to the second detailed route proposal submitted by EBPC were considered during a hearing held in Saint John, New Brunswick, on 9 July 2008.

A compilation of recent decisions regarding the detailed route hearings for the Emera Brunswick Pipeline in a single blue book document was released on 30 September 2008.

Contact Information

Media Relations Team
Canada Energy Regulator
Email: media@cer-rec.gc.ca
Telephone (toll free): 1-800-899-1265

News Releases

  • 2008-05-13
    NEB issues a Compilation of its Decisions on Brunswick Pipeline's Detailed Route
  • 2008-03-03
    NEB decides on a portion of the proposed Brunswick Pipeline Detailed Route
  • 2007-11-26
    NEB to hold public hearing on detailed route of Emera Brunswick Pipeline
  • 2007-10-25
    NEB is seeking comments on three segments to Emera Brunswick Pipeline Routing

Regulatory Documents