ARCHIVED - TransCanada Pipelines Limited - Audit Report OF-Surv-OpAud-T211-2012-2013 01 - Appendix IV - TransCanada OPR-99 Integrity Management Program Audit - Documents Reviewed
This page has been archived on the Web
Information identified as archived is provided for reference, research or recordkeeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.
Appendix IV
TransCanada OPR-99 Integrity Management Program Audit
Documents Reviewed
15-11-2012 Letter IMPs and Commitment Statement
- 01 CDN-LIQ-IMP Liquids IMP Rev 02 DRAFT 5742060.pdf
- 02 CDN-GAS-IMP Canadian Gas Pipeline IMP 3892900.PDF
- 03 Plant IMP 3899337.pdf
- 04 Pipe Integrity Commitment Statement 7058269.pdf
- 05 TEP-INT-DOC Pipe Integrity Doc Control 6765885.pdf
- 06 Letter to NEB IMPs 15Nov12.pdf
2012-11-27 - Additional TransCanada Materials
- TransCanada Aerial Pipeline Patrol TOP Nov. 27.pdf
- TransCanada Incident and Issue Mgmt Program.pdf
- TransCanada Incident Mgmt Classification Guide 3976290.pdf
- TransCanada Issues Mgmt Classification Guide 3976292.pdf
- TransCanada Pipeline Public Awareness Program - TOP Nov. 27.pdf
- TransCanada PL Crossing and Encroachment Proc. Canada - TOP Nov. 27.pdf
- TransCanada PL Ground Based Patrols TOP Nov. 27.pdf
2012-11-29 Elements 3.1 and 4.2 - Nov 29 12
- Element 3.1 Org Structure Roles and Responsibilities Re-draft Nov 29 12.pdf
- Element 4.2 Corrective and Preventive Actions Draft Nov 22 2012.pdf
- Letter to NEB Audit General Confidentiality 22Nov12 (2).pdf
2012-12-06 Elements 2.1 and 4.4 - Dec 6 12
- 01 Element 2.1 Hazard ID, Risk Assess, Control Dec 6 12.pdf
- 02 Integrity Management System.pdf
- 03 Asset Management System Framework.pdf
- 04 Element 4.4 Internal Audit Dec 6 12.pdf
2012-12-06 Elements 3.3 and 5.1 - Dec 6 12
- Element 3.3 Training Competence and Evaluation - Re-Draft Dec 6.pdf
- Element 3.3 Training Competence and Evaluation First Draft Nov 29 12.pdf
- Element 5.1 Management Review Draft Nov. 29 12.pdf
- TEP-INT-MREV Pipe Integrity Mgmt Review Proc.pdf
2012-12-12 TransCanada Materials Provided to NEB
- TEP-ITM-ECOR-CDN External Corrosion Threat Management Program (CDN) 6570955.pdf
- TEP-ITM-EQUIP Equipment Failure Threat Management Program 6786449.pdf
- TEP-ITM-IC Internal Corrosion Threat Management Program (Cdn-US) 6786402.pdf
- TEP-ITM-IOPS Incorrect Operations Threat Management Program 6810297.pdf
- TEP-ITM-MANUF-CDN Manufacturing, Fabrication and Construction Threat Management Program (Cdn) 6786458.pdf
- TEP-ITM-MECH Mechanical Damage Threat Management Program (CDN-US-MEX) 6786487.pdf
- TEP-ITM-SCC-CDN Stress Corrosion Cracking Threat Management Program 6786458.pdf
- TEP-ITM-WOF Weather and Outside Forces (Geotechnical and Meteorological) Threat Management Process (Cdn-US-Mex) 5767611.pdf
2012-12-14 Elements 3.6, 3.7 and 4.1 - Dec 14
- 3.6 NEB Audit Evaluation - Operational Control - Normal Operations Dec 14 12.pdf
- 3.7 NEB Audit Evaluation - Ops Control - Upset or Abnormal Ops Dec 14 12.pdf
- 4.1 NEB Audit Evaluation - Inspection Measurement and Monitoring Dec 14 12.pdf
2012-12-14 TransCanada Materials Provided to NEB
- TransCanada Corrective and Preventive Actions DRAFT 3 Dec 14.pdf
- Presentation - NEB Audit 2.1 - Hazards Ident.pdf
- Presentation - NEB Audit 4.4 - Internal Audits.pdf
- TransCanada - Scope of PIMP and FIMS.pdf
2012-12-18 TransCanada Materials Provided to NEB
- Presentation KPIs and Corrective and Preventive Measures Dec 6.pdf
- Presentation 3.6 Introduction and Normal Operations Dec 14.pdf
- Presentation 3.7 Upset or Abnormal Operating Conditions Dec 14.pdf
- Presentation 4.1 Inspection Measurement and Monitoring Dec 14.pdf
- TransCanada - ECOR (CDN) Scorecard.pdf
- TransCanada - Leaks and Ruptures Scorecard.pdf
- TransCanada - SCC Scorecard.pdf
2012-12-19 TransCanada Materials Provided to NEB
- TransCanada - Facilities Control Integ Plan Internal Audit Report 2011.pdf
- TransCanada - Pipeline Integrity Mgmt Program Review 2010.pdf
- TransCanada KPIs - Performance Measures.pdf
2012-12-21 Elements Re-draft 2.1, 3.6, 3.7, 4.1 and related docs Dec 21
- 2.1 NEB Audit Evaluation - Hazard ID, Risk Assess, Control Redraft Dec 21 2012.pdf
- 3.6 NEB Audit Evaluation - Operational Control - Normal Operations Redraft Dec 21 2012.pdf
- 3.7 NEB Audit Evaluation - Ops Control Upset or Abnormal Ops Redraft Dec 21 2012.pdf
- 4.1 NEB Audit Evaluation - Inspect Measure and Monitor Redraft Dec 21 2012.pdf
- TQM Threat Identification and Risk Assess Dec 21 2012.pdf
- TransCanada Presentation - Update to NEB 22-06-2012_Dec 21 2012.pdf
2013-01-31 TransCanada Materials Provided to NEB
- Table 3 3-1.doc
2013-02-08 - ITM Performance Measures - Scorecards
- Construction - Integrity Threat Management Scorecard.pdf
- Equipment - Integrity Threat Management Scorecard.pdf
- Incorrect Operations - Integrity Threat Management Scorecard.pdf
- Internal Corrosion - Integrity Threat Management Scorecard.pdf
- Manufacturing - Integrity Threat Management Scorecard.pdf
- Mechanical Damage - Integrity Threat Management Scorecard.pdf
- Weather Outside Forces - Integrity Threat Management Scorecard.pdf
2013-02-14 NEB Audit Information Request Responses Round 2
NEB AIR 2-1.1 to 2-1.4
- NEB AIR 2-1.1 - Final Response 15Feb13.pdf
- NEB AIR 2-1.2 - Final Response 15Feb13.pdf
- NEB AIR 2-1.3 - Final Response 15Feb13.pdf
- NEB AIR 2-1.4 - Final Response 15Feb13.pdf
- NEB AIR 2-2.1 - Final Response 15Feb13.pdf
- NEB AIR 2-2.2 - Final Response 15Feb13.pdf
- NEB AIR 2-2.3 - Final Response 15Feb13.pdf
- NEB AIR 2-2.4 - Final Response 15Feb13.pdf
Records Supporting NEB AIR 2-1
- Corrective and Preventive Action Procedure 006262052.pdf
- CPMS Control of Records 006416311.pdf
- CPMS Internal Audit Procedure 006271464.pdf
- CPMS Manage Continual Improvement 006556411.pdf
- CPMS Manage Project Design (006740639).pdf
- CPMS Manage Project Turnover 007044410.pdf
- CPMS NEB Summary.pdf
- CPMS One Page.pdf
- CPMS Overview_08Feb13.pdf
- CPMS Scope Diagram.pdf
- Lessons Learned Procedure 003788443.pdf
- Major Project O&E Functional Engineering and Support 007218421.pdf
- NEB AIR 1.4 Example - Project Turnover to Operations Deliverables List
(Parkway Loop Project).pdf - TEP-QUAL-ESM-DOC Document Control Procedure (Cdn-US-Mex) 003764703.pdf
- TransCanada Nonconformance Procedure (006556411).pdf
Records Supporting NEB AIR 2-2
- 2011 Annual Geotechnical Threat Management PMP Activities Report - WOF 007765534.pdf
- 2012 Oct - Pipe Integrity Business Review Meeting Presentation (redacted).pdf
- 2012 Process Review Weather and Outside Forces TEP-ITM-WOF - Meeting Minutes 007773954.pdf
- 2012-02-11 IIT Action Report - PGC.pdf
- 2013 Canadian Corrosion Program.pdf
- 2013 PI Keystone Maintenance Plan.pdf
- Canadian Liquid Integrity Management Program CDN-LIQ-IMP Dec 2012.pdf
- CPO Capital Project Performance Report - Dec 2012 7822977.pdf
- ICAM Scorecard Program Planning Example.pdf
- IIT Overview TEP-INT-COMM.pdf
- IIT Report - Feb. 1, 2013.pdf
- Integrity Plan Revision, Review and Approval Process 4497609.pdf
- Integrity Plans 101 4786600.pdf
- Liquid Pipeline Systems Assessment Plan TER-AP-LIQ-CDN 005933450.pdf
- NEB AIR 2.2.4 OE December 2012 data block.pdf
- NEB AIR 2.2.4 Reference Summary of O_E Scorecard.pdf
- Pipe Integrity Business Review Meeting Q3 2012 Keystone.pdf
- Quality Team Meeting 7 Agenda Nov 28 2012 (2).pdf
- RB211 2012 Integrity Plan 6995890.pdf
- TOPs Report.pdf
2013-03-12 NEB Audit Meeting Documents Provided
- TEP-ILI-DEF-CDN Analysis of Deformation ILI Data for CDN Pipelines 6980190.pdf
- TEP-INT-CLA Class Analysis and Remediation (CDN) 5766974.pdf
- TEP-INT-ILI-CDN Analysis of MFL In Line Inspection (ILI) Data for CDN Pipelines 6570876.pdf
- TEP-INT-PR Pipe Integrity Management - Process Review Procedure 6522487.pdf
- TEP-ITM-FPIPE-CDN Facilities Piping Integrity Management Program (CDN) 7379193.pdf
2013-03-14 NEB Audit Meeting Documents Provided
- TEP-CP-PRGM Corrosion Prevention Program (Cdn-US-Mex) 6786483.pdf
2013-03-18 Pressure Vessel Integrity Material
- 0.1 QMS Pressure Vessels 2011.pdf
- 0.2 PRESSURE VESSEL INTEGRITY PLAN.pdf
- 0.3 PRV INTEGRITY PLAN.pdf
- 06.1 training list.pdf
- 06.2 John ISPVC certificate.pdf
- 06.3 Bill Yang's Qualification Summary.pdf
- 06.4 training schock.pdf
- 06.5 owners inspector training list.pdf
- 08.1 Approved Manufacturers List REDACTED.pdf
- 08.2 SMS Service Listing- Testing.pdf
- 09 sample calibration cert.pdf
- 10.1 screenshot Avantis Hierarchy.pdf
- 10.3 TOP Pressure vessel Integrity External Inspection.pdf
- 10.4 TOP scrubber vessel inspection.pdf
- 10.5 TOP strainer vessel inspection.pdf
- 10.6 TOP Pressure Relief Valve Inspection.pdf
- 10.7 TOP Feedback.pdf
- 11.1 API 510_e9.pdf
- 11.1A API 576_e3.pdf
- 11.2 AB-506 ABSA standard.pdf
- 11.3 CDN Gas Leaks Only Q4-2012.pdf
- 11.3a PSV failure trending.pdf
- 11.3b Gas Leak Analysis feedback.pdf
- 11.4 vessel inspection documents.pdf
- 11.5 vessel and piping UT data.pdf
- 12 Repair of heating Boiler.pdf
- 13.1 TES-MATL-PV1.pdf
- 13.2 design data.pdf
- 13.4 3PI manufacturing inspection.pdf
- 13.6 Completion of Construction.pdf
- 13.7 commissioning docs 1.pdf
- 13.8 commissioning docs 2.pdf
- 13.9 AB-10 change of status.pdf
- 16.01 Internal Audit procedure for QMS.pdf
- 16.02 Internal Audit QMS 2012.pdf
- 16.03 ABSA External Audit QMS-8119 2011.pdf
- 16.03a ABSA External Audit Completion 2011.pdf
- 16.04 QMS 2011 Internal Audit Report.pdf
- 16.05 QMS 2010 Internal Audit Report.pdf
- 16.06 Pressure Relief Valve Audit Procedure R2.pdf
- 16.07 Tunis Station 102 Relief valve Audit pictures.pdf
- 16.08 Tunis Station 102 Relief Valve Audit.pdf
- 16.11 QMS Internal Audit checklist 2012.pdf
- 18.2 IIT 194030 Provincial Inspection Findings.pdf
- 19.02 IIT180040 Stn45 FG heater.pdf
- 19.03 IIT180040 Investigation Stn45 FG heater.pdf
- 19.04 Metallurgical Report IIT180040.pdf
- 19.05 MOC Stn45 FG heater.pdf
- 19.06 TOP HVAC.pdf
- 19.07 IIT1161890 Norwalk FG filter.pdf
- 19.08 IIT 161890 Investigation FG filter.pdf
- 19.09 Norwalk inspection.pdf
- 19.10 Compressed Air Systems Integrity Plan.pdf
- 19.99 CDN Gas Leaks Only Q4-2012.pdf
- 19.99 Gas Leaks and Releases Q4-2012.pdf
- 19.99a PSV failure trending.pdf
- 19.99b Gas Leak Analysis feedback.pdf
- 20.1 LMS owners inspector.pdf
- 20.2 owners inspector training.pdf
- 21.1 MOC.pdf
- 22.1 Station 45 heater failure DIR.pdf
2013-03-19 Facilities - Controls - Automation Engineering Material
- A - Compressor Station Pressure Limits and Settings Canada.pdf
- B - Control and Monitoring Inspection.pdf
- C - Emergency Shutdown System Inspection.pdf
- D - Emergency Shutdown System M12 Inspection Station 116C 2011 M12 ESD Checklist WO 682966-1.pdf
- E - Station 1211 Work Orders.pdf
- F - Station Control System Procedure.pdf
- G - Station Control System Commissioning Checksheet.pdf
- H - SCADA Commissioning Guide Rev 0.pdf
- I - Station 1211 Station Control System Upgrade.pdf
- J - IIT 246462 Station 1211 Control System Design Change.pdf
2013-03-19 Facilities - Mechanical - Compressor Stations Material
- COM 1 Approved Manufacturers List.pdf
- COM 3 PSSR.pdf
- DES 1 Excerpt HPG Guiding principal.pdf
- DES 2 HL Station Relief Valve Re-IFP.pdf
- INT IIT 1 CDN Gas Leaks Only Q4-2012.pdf
- INT IIT 2 PSV failure trending.pdf
- INT IIT 3 Gas Leak Analysis feedback.pdf
- INT 1 PRV INTEGRITY PLAN.pdf
- INT 2 QMS Pressure Equip 2011.pdf
- INT 3 Tunis Station 102 Relief Valve Audit.pdf
- INT 4 PRV Audit Procedure R2.pdf
- INT 5 Tunis Station 102 PRV Audit pictures.pdf
- INT T1 John ISPVC certificate.pdf
- INT T2 Bill Yang's Qualification Summary (3).pdf
- INT T3 owners inspection training list.pdf
- MTC 1 TOP Pressure Relief Valve Inspection.pdf
- MTC 10 API 576_e3.pdf
- MTC 11 AB-506.pdf
- MTC 2 TOP Inspection and Cycle test for Emergency valves.pdf
- MTC 3 TOP Surge Valve Set-point Verification.pdf
- MTC 4 Vendor service reports.pdf
- MTC 5 Avantis data.pdf
- MTC 5a Avantis screenshot.pdf
- MTC 5b Avantis screenshot.pdf
- MTC 6 NCR List vessels.pdf
- MTC 7 194030 Provincial inspection findings.pdf
- MTC 9 TOP Feedback.pdf
- OPS 1 TOP Facilities Integrity Inspections.pdf
- QMS Pressure Equipment 2011.pdf
2013-03-19 Facilities - Mechanical - Pipe, Valve Integrity Material
- 01 Valve Integrity Mail box snapshot.pdf
- 02 TEP_ITM_IOPS Incorrect Operations Threat Management Program.pdf
- 03 TEP-ITM-EQUIP Equipment Failure Threat Management Program.pdf
- 04 2013 PMP approval document example.pdf
- 05 Pipeline Pressure Relief Valve Blow off Valve Inspection.pdf
- 06 Valve and Valve Operator Inspection and Servicing.pdf
- 07 Valve and Valve Operator Leak Inspection and Cycle Test (Canada).pdf
- 08 Control Valve Inspection Canada and Mexico.pdf
- 09 Alberta System (Down Stream of Delivery Stations) Over Pressure Protection Devices.pdf
- 10 Mainline Over Pressure Protection Devices (Canada).pdf
- 11 Critical Gas Pressure Regulator Inspection and Maintenance.pdf
- 12 Non Critical Gas Pressure Regulator Inspection and Maintenance.pdf
- 13. Valve and Valve Operator Leak Inspection and Cycle Test for Emergency valves.pdf
- Example. auto blowoff inspection track.wo 726096.pdf
- Example. Control Valve inspection track.wo741331.pdf
- Example. Slam shut inspection track.wo725105.pdf
2013-03-19 Facilities - Mechanical - Tanks Material
Hardisty Tank Inspection and TOP Feedback Process
- 2007 Pass Creek West Underground Drip tank M36 Inspection.pdf
- 2007 Underground Drip Tank Inspection M36 Inspection.pdf
- Aboveground Tank Containment Area Inspection 2009 Shelbyville 005787568.pdf
- CS - Central - Cavendish - 2010 Test report.pdf
- CS - WR - Beaver Creek - 2002 Test Inspection 005370386.pdf
- CS-WR-Buffalo Creek - 2001 Test Report 005370396.pdf
- IIT 144757 French Man River sample.pdf
- MS - WR - High River East - 2011 006495829.pdf
- Revision 3 Frenchmar River Underground Tank Leak Report and Findings 003823430.pdf
- Tanks Inspections test reports wildrose.pdf
- TransCanada reports and Invoices Leak technologies 2012 (2).pdf
- TransCanada reports and Invoices Leak technologies 2012.pdf
- Underground Drip tank Inspection Athabasca.pdf
- Underground Drip Tank Inspection Prosperity.pdf
- Underground Drip tank Inspection Record Kaybob 2013 006232688.pdf
- Underground drip tank inspection screen shot EDMS search 1.pdf
- Underground drip tank inspection screen shot EDMS search 2.pdf
- Underground drip tank inspection screen shot EDMS search 3.pdf
- Underground drip tank inspection screen shot EDMS search.pdf
- Underground Drip Tank M36 Inspection00.pdf
- Underground Drip Tank M36 Inspection01.pdf
- Underground Drip Tank Test Alta Beaver Creek.pdf
- Underground Drip Tank Test Berland River.pdf
- Underground TOP version history.pdf
Tank Integrity Program TOP History
- 1.1 Presentation screen shots.pdf
- 1.1.2 API 653 TOPs screen shot.pdf
- 1.2 Canada Tanks Bar graph.pdf
- 1.2.1 Screen Shot Existing TOPs.pdf
- 1.2.2 Screen Shot TOP feedback completed.pdf
- 1.2.3 Screen shot feedback answer.pdf
- 1.3 - API 653 Aboveground Storage Tank Inspection.pdf
- 1.3.1- API 653 Aboveground Storage Tank Monthly or Weekly Inspection Form.pdf
- 1.3.2 - API 653 Aboveground Storage Tank Out of Service Inspection Form.pdf
- 1.4 - Storage Tank Inspection and Testing Excludes API 650 or API 12C.pdf
- 1.5 - Underground Drip Tank Inspection.pdf
- 1.5.1 Underground Drip Tank Inspection Record.pdf
- 1.5.2 Underground Drip Tank Testing Summary.pdf
- 1.6 Aboveground Storage Tank Cleaning Form.pdf
- 1.7 Aboveground Storage Tank Repairs Form.pdf
- 3 Screen Shot Avantis Data.pdf
- 3.1 Screen Shot PM Plan Tk 01.pdf
- 3.2 Screen Shot Activity History Tank 01.pdf
- 3.3 Screen Shot PM Task info.pdf
- Aboveground Hardisty tank PM Plan screen shot Work History.pdf
- Aboveground Hardisty tank PM Plan screen shot.pdf
- Aboveground Hardisty tank screen shot Work Task.pdf
- Aboveground Tank Inspection Hardisty Tank 1.pdf
2013-04-19 - Data Room Requests ECOR SWRA (PRIME)
- 2013 Budget CND ECOR Redacted.pdf
- AB 2013 PRIME Risk Assessment - Final Results.pdf
- Finalized SWRA Data.pdf
2013-05-01 PRIME 2013 Results
- 2013 PRIME Foothills Final Results.pdf
- 2013 PRIME Mainline Final Results.pdf
- 2013 PRIME Mainline Final Results.xls
- 2013 PRIME TQM Final Results.pdf
2013-05-06 2013 SWRA Data
- 2013 SWRA Foothills Data.pdf
- 2013 SWRA Mainline Data.pdf
- 2013 SWRA TQM Data.pdf
2013-05-08 IC Follow Up Response
- 2012 IC Susceptible Lines with GQ Issues Review.xls
- AITF Sludge Corrosion Testing and Chemical Analysis v6.pdf
- Craigend East - 10 years Gas Quality Data.pdf
- Craigend East - Non-Compliance Water Content Letter.pdf
- NEB - Internal Corrosion response - final.pdf
2013-06-10 Canadian External Corrosion
- NEB Interview Action Item AIR No3 Observation 1.1 and 1.2 June 2013.pdf
- NEB Interview Action Item AIR No3 Observation 1.3 June 2013.pdf
- NEB Interview Action Item AIR No3 Observation 1.4 June 2013.pdf
- NEB Interview Action Item AIR No3 Observation 1.5 June 2013.pdf
- NEB Interview Action Item AIR No3 Observation 1.6 June 2013.pdf
- NEB Interview Action Item AIR No3 Table 1a and Table 2a.pdf
2013-06-14 Facility Piping AIR
- NEB AIR Non Sour Service - Follow Up.pdf
2013-07-09 FIRM Document
- Facility Integrity and Reliability Management Program (CDN-US-MEX) 7803540.pdf
Day 1 - 4 Risk Items - Consolidated Response
- Appendix C - Tech Memo EMAT Analysis rev1.pdf
- Appendix E 2010 Golders field assessment draft.pdf
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
- Prime Technical Documentation APPENDIX A 8041010.pdf
- Prime Technical Documentation APPENDIX B 8041012.pdf
- Prime Technical Documentation APPENDIX C 8041014.pdf
- Prime Technical Documentation APPENDIX D 8041034.pdf
- Prime Technical Documentation APPENDIX E 8041038.pdf
- Prime Technical Documentation APPENDIX F 8041040.pdf
- Prime Technical Documentation APPENDIX G 8041042.pdf
- Prime Technical Documentation APPENDIX H 8041044.pdf
- PRIME Technical Documentation July 2006 8041008.pdf
- TEP-INT-PRIME Risk Assessment Using PRIME 003972569.pdf
- TER-COR-RSK Risk Models for Corrosion using ILI Data 5767603.pdf
- TER-RISK-CON - 2009 Consequence Models within PRIME (highlighted) 5767605.pdf
- TER-RISK-CON Consequence Models Within System Wide Risk Assessment and Integrity Management 7326298.pdf
- TER-RISK-SWR- 2009 System Wide Risk Assessment (highlighted) 5767607.pdf
- TOP Pipeline Inspection Report 3841211.doc
- TOP Pipeline Right Of Way Procedures Canada 3672613.pdf
- TransCanada Aerial Pipeline Patrol TOP Nov. 27.pdf
- TransCanada Pipeline Public Awareness Program - TOP Nov. 27.pdf
- TransCanada PL Crossing and Encroachment Proc. Canada - TOP Nov. 27.pdf
- 2013 Mar 12 - Performance Indicators Report for 2012 - Pipe Integrity - Risk 8029673
Day 1 March 12 - (EC) External Corrosion and Dent Program
10 Action - PRIME risk assessment
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
11 Action - Facilities Piping TEP
- TEP-ITM-FPIPE-CDN Facilities Piping Integrity Management Program (CDN) 7379193.pdf
2 Obs - Communication of EC Program
- 2 Observation ECOR - NEB Response - TEP-INT-ILI-CDN.pdf
- 2 Observation ECOR - NEB Response - TEP-ITM-ECOR-CDN.pdf
- CDN-GAS-IMP Canadian Gas Pipeline Integrity Management Program 003892900.pdf
- MOC 12-065 Revision of TEP-INT-ILI-CDN 007722164.pdf
- MOC 12-066 Revision of TEP-ITM-ECOR (Cdn) 007722167.pdf
- TEP-INT-ILI-CDN Analysis of MFL ILI Data 006570876.pdf
- TEP-INT-MOC Pipe Integrity - Management of Change Procedure 006425143.pdf
- TEP-ITM-ECOR-CDN External Corrosion Threat Management Program 006570955.pdf
- TES-CORR-PMP Corrosion Pipeline Maintenance Plan Development 005767609.pdf
4 Action - EC Process Review and Annual EC Reports
- Pipe Integrity Process Review - External Corrosion (ECOR) Canada (EDMS 007728805) (in data room)
- Canadian External Corrosion Pipeline Maintenance Plan (PMP) Annual Report for 2012 (EDMS 008055282) (in data room)
- Canadian External Corrosion Pipeline Maintenance Plan (PMP) Annual Report for 2011 (EDMS 008038129) (in data room)
6(a) Action - RA Consequence Inputs and Outputs
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
6(b) Action - Societal Risks and Individual Risks
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
6(d) Action - Unpiggable segment seriatim
- 2013 Budget Presentation - CDN ECOR 008037970.pdf
- 6d Action ECOR - NEB Response - Unpiggable segment.pdf
- TEP-INT-PRIME Risk Assessment Using PRIME 003972569.pdf
- TEP-ITM-ECOR-CDN External Corrosion Threat Management 006570955.pdf
- 2011 Pipeline Maintenance Plan (PMP) Annual Report (EDMS No. 008038129) (Data room)
- 2012 Pipeline Maintenance Plan (PMP) Annual Report (Data room)
6(e) Action - Top 10 Unpiggable
- 6e Action ECOR - NEB Response - Top 10 Unpiggable.pdf
- PRIME Technical Documentation 008041008.pdf
- Prime Technical Documentation APPENDIX A 8041010.pdf
- Prime Technical Documentation APPENDIX B 8041012.pdf
- Prime Technical Documentation APPENDIX C 8041014.pdf
- Prime Technical Documentation APPENDIX D 8041034.pdf
- Prime Technical Documentation APPENDIX E 8041038.pdf
- Prime Technical Documentation APPENDIX F 8041040.pdf
- Prime Technical Documentation APPENDIX G 8041042.pdf
- Prime Technical Documentation APPENDIX H 8041044.pdf
- PRIME Technical Documentation July 2006 8041008.pdf
- TEP-INT-PRIME Risk Assessment Using PRIME 003972569.pdf
- TEP-ITM-ECOR-CDN External Corrosion Threat Management Program 006570955.pdf
- 2013 SWRA Alberta Final Results.xls (Data Room)
- Finalized SWRA Data.xlsx (Data Room)
6(f) Action - Number of Unpiggable
- 2013 Budget Presentation - CDN ECOR 008037970.pdf
- 6f Action ECOR - NEB Response - Number of Unpiggable.pdf
- NC Technical Memo TM 1347 Relative Failure Frequency of Large Diameter vs Small Diameter.pdf
- Nova Chemicals TR 2283 Relative Failure Frequency on Small versus Large Diameter Pipe.pdf
- 2011 Pipeline Maintenance Plan (PMP) Annual Report (EDMS No. 008038129) (Data Room)
- 2012 Pipeline Maintenance Plan (PMP) Annual Report (Data Room)
6(g) Action - Incorporation of CP Data
- NEB Response - See folder 'Day 1 - 4 Risk Items - Consolidated Response'
6(h) Action - CP Data in EC RA
- 6h Action - NEB Response - CP Data in EC RA.pdf
- TEP-ITM-ECOR-CDN External Corrosion Threat Management 006570955.pdf
- AB CP.xls (Data Room)
- 2013 AB Summary.xlsx (Data Room)
6(i) Action - Interaction of Threats
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
7 Action - EC Performance Measures
- 7 Action ECOR - NEB Response - Performance Measures.pdf
- TEP-ITM-ECOR-CDN External Corrosion Threat Management 006570955.pdf
- Canadian External Corrosion Pipeline Maintenance Plan Annual Report for 2012
9(c) Action - Dent Eng Assessments
- 9c Action ECOR - NEB Response - Dent Eng Assessments.pdf
- ANG Kootenay - Kingsgate DENT Strain Analysis Report.pdf
- MLV45-52-1 dent strain report - Caliper.pdf
- PR-218-063511Development of a Model for Predicting the Severity of Pipeline Damage Identified by In-Line Inspection.pdf
- Technical Memo - MLV46-52-1 DNT Assessment.pdf
- Technical Memorandum - ANG Kootenay-Kingsgate Dent Assessmen.pdf
- TEP-ILI-DEF-CDN Analysis of Deformation In-Line Inspection Data 006980190.pdf
9(d) Action - Dent TEP and CP TEP
- TEP-CP-PRGM Corrosion Prevention Program (Cdn-US-Mex) 6786483.pdf
- TEP-ILI-DEF-CDN Analysis of Deformation ILI Data for CDN Pipelines 6980190.pdf
9(e) Action - Dent program consequences
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
9(f) Action - Dent with no high res tool
- 9f Action ECOR - NEB Response - Dents with no high resolution tool.pdf
Day 2 March 13 - (CP) Cathodic Protection
1 Action - CP over potentials
- 1 Action CP - NEB Response - CP Overprotection.pdf
- IPC2002 27267 Permeable Coatings and CP Compatibility.pdf
- IPC2004 000570 Long Term FBE Performance.pdf
- TES-PIPE-EW Specification for Electric Welded Pipe (CDN) 3670788.pdf
- TES-PIPE-SAW Specification for Double Submerged Arc Welded Pipe 3776714.pdf
- WIC Example 7932-313_FINAL.PDF
2 Action - CP on potential surveys only
- 2 Action CP - NEB Response - ON Potential Criteria.pdf
- 900mV ON Memo 2003.pdf
- Nova Criteria Study.pdf
- Prairie ON Criteria Study.pdf
- TES-CP-CR Cathodic Protection Criteria Specification 003678793.pdf
3 Action - CP Annual Report
- Corrosion Prevention Pipeline Maintenance Plan Annual Report for 2012 Alberta and BC (in data room)
- Corrosion Prevention Pipeline Maintenance Plan Annual Report for 2012 - MLV 2-16 (in data room)
- Corrosion Prevention Pipeline Maintenance Plan Annual Report for 2012 - MLV 16-58 (in data room)
- Corrosion Prevention Pipeline Maintenance Plan Annual Report for 2013 in NONT and EONT (in data room)
- Corrosion Prevention Pipeline Maintenance Plan Annual Report for 2012 (Overall Canada Summary, with KPI’s) (in data room)
5 Obs - CP low potential survey prioritization
- 5 Observation CP - NEB Response - CP Prioritization.pdf
Day 2 March 13 - (SCC) Stress Corrosion Cracking
1 Action - SCC Annual Report
- 1 Action SCC - NEB Response - SCC Annual Report.pdf
- SCC Pipeline Maintenance Plan Annual Report for 2012.(in data room)
2 Action - Monthly Threat Interaction Meetings
- 2 Action SCC - NEB Response - Monthly Threat Interaction Meetings.pdf
- Shared Group Activities Meeting December 2010.pdf
- Shared Group Activities Meeting Minutes_May_2012.pdf
- Shared Group Activities Meeting Minutes_November_2011.pdf
- Shared Group Activities Meeting Minutes_October_2012.pdf
3 Action - SCC Program deliverables
- 3 Action SCC - NEB Response - SCC Program Deliverables.pdf
- Evidence 002 - SCC Cost Reasoning Spreadsheet.pdf
- Evidence 003 - 2161505_PI2011 Mainline EMAT Inspection MLV 130 - 139 Line 1.pdf
- Evidence 004 - 2168666_PI2011 Post-ILI SCC Excavations from EMAT run between MLV 130-139 Line 1.pdf
- Evidence 005 - 2171464_PI2011 SCC Extra EMAT Data Analysis between MLV 130-139 Line 1.pdf
- Evidence 001: 2012 Process Review SCC TEP-ITM-SCC-CDN Meeting Notes (in data room)
4 Action - SCC risk assessment consequences
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
5 Action - SCC high pH
- 5 Action SCC - NEB Response - High pH SCC Management.pdf
- GE EMAT Specfication.pdf
- Rosen EMAT Specification.pdf
- TES-ILI-EMAT Specification for EMAT In-Line Inspection Technologies (CDN).pdf
6 Action - SCC fatigue growth
- 2012-01-12 - 2012 Eastern Mainline Expansion s58 Application Responses to NEB Information Requests NEB 1-7 Part A.pdf
- 6 Action SCC - NEB Response - Fatigue Crack Growth.pdf
- CEPA study on Characterization of Pipeline Pressure Fluctuations in Terms Relevant to Stress Corrosion Cracking.pdf
- MLV 107-2 Engineering Assessment of Line 2 Report.pdf
- MLV 76-2 Acuren Investigation.pdf
Day 2 March 13 - (WOF) Weather and Outside Forces
1 Action - WOF TEP revisions
- 1 Action WOF - NEB Response - WOF TEP Revisions.pdf
12 Obs - WOF risk assessment consequences
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
13 Obs - WOF influence on ROW patrol program
- 13 Obs WOF - NEB Response - WOF Influence on ROW patrol program.pdf
- TOP Aerial Pipeline Patrol 3672387.pdf
2 Action - WOF process review
- (Data Room) 2012 Process Review TEP-ITM-WOF Weather and Outside Forces Management Program Meeting Minutes 7773954.pdf
2 Obs - Reference to CSA Z662-07
- 2 Observation WOF - NEB Response - Reference to CSA Z662-07.pdf
- (Data Room) 2012 Process Review TEP-ITM-WOF Weather and Outside Forces Management Program Meeting Minutes 7773954.pdf
4 Action - Phase 1 surveys
- 1999 - AB - Phase I Implementation of Rainfall Ground Mvt Models Action Item 4.pdf
- 2001 - AB - Visual Inspection of 11 slopes - Evidence 3.pdf
- 2003 SI Installations Cranberry Creek Lateral - Evidence 4.pdf
- 4 Action WOF - NEB Response - Phased Surveys.pdf
- CND Keystone Phase I Geohazard Analysis 2010_Action Item 4.pdf
- Pembina River Slope Monitoring _Edson Mainline Evidence 6.doc
- Evidence 005 2000 Assessment of Slope Movement Potential, Site Visit Report (in data room)
7 Action - Soil erosion - flooding threat
- 7 Action WOF - NEB Response - Soil erosion flooding threat.pdf
- TOP Pipeline Underwater Inspections 003671756.pdf
99 Action - TOPs and WOF annual report PR process review
- 99 Action WOF - NEB Response - Requested Documents.pdf
- TOP Aerial Pipeline Patrol 3672387.pdf
- TOP Pipeline Underwater Inspections 3671756.pdf
- 2012 Process Review Management Systems TEP-INT-PR - Meeting Minutes 7898342 (in data room)
- Weather and Outside Forces Pipeline Maintenance Plan Annual Report for 2012 8029726 (in data room)
Day 3 March 14 - (IC) Internal Corrosion
6(f) Action - Coincident dig sites
- 6f Action IC - NEB Response - Coincident Dig Sites.pdf
6(h) Action - IC annual report
- 6h Action IC - NEB Response - IC Annual Report .pdf
- 1. 2012 PMP Annual Report IC Canada EDMS No. 008029989 (in data room)
6(j) Obs - RA and Prioritizations
- 6j Observation IC - NEB Response - Completion of IC Program.pdf
- Ref 2_2012 IC Susceptible Lines.xlsx
- Ref 3_2013 Approved PMP Budget ICOR Redacted.pdf
- Ref 4_Dec Sum for 2013 IC Corrosion Coupons and Solids-Liquids Sampling - Financials Redacted.pdf
6(k) Action - IC process review
- 6k Action IC - NEB Response - IC Process Review .pdf
Day 3 March 14 - (MFC) Manufacturing Fabrication and Construction
1 Action - PHMSA Advisory on Pipe
- 1 Action MFC - NEB Response - PHMSA Advisory on Pipe.pdf
- Response to NEB Audit in Regards to Pipe Manufacturing Threats for New Pipe Manufacturing 13 03 17.pdf
2 Action - R ratios
- 2 Action MFC - NEB Response - R Ratios - Supplemental.pdf
- 2 Action MFC - NEB Response - R Ratios.pdf
- Reference 1 Pressure Data for Western Mainline (Cabri CS).pdf
- Reference 2 Pressure Data for Line 2 in Northern Ontario (Dryden CS).pdf
- Reference 3 Pressure Data for Canadian Mainline Toronto - Montreal, Youngstown Pipe Line (Cobourg CS).pdf
2 Obs - MFC consequence
- NEB Action Items - Consolidated Risk Response Mar 28.pdf
6 Obs - TC audit plan
- 6 Action MFC - NEB Response - TC Audit Plan.pdf
- TEP-NDT-ADT Procedure for Non-Destructive Examination (NDE) Audits 3797402.pdf
7 Obs - Low Strength fittings
- 7 Observation MFC - NEB Response - Validation of Existing Fittings.pdf
Day 3 March 14 - Liquid IMP - Keystone
1 Action - Purchasing substandard materials
- 1 and 2 Action Liquid IMP - NEB Response - Validation of Pipe and Fittings.pdf
- Various documents in data room
2 Action - Low Strength Fittings
- 1 and 2 Action Liquid IMP - NEB Response - Validation of Pipe and Fittings.pdf
- 2 Action Liquid IMP - NEB Response - Below Spec Fittings.pdf
- Liquid Pipeline Systems Assessment Plan TER-AP-LIQ-CDN 005933450.pdf
3 and 4 Actions - Non Sour Keystone Service
- Non Sour Keystone Service Liquid IMP - Action Items 3 and 4.pdf
- Non Sour Service of Keystone - Addendum - 2013-03-20.pdf
- TransCanada Hydrocarbon Exposure Control Procedures TOP EDMS 005528684.pdf
- TransCanada Hydrogen Sulphide Exposure Control TOP EDMS 003671879.pdf
- TransCanada Portable Gas Detection of the Atmosphere TOP EDMS 003835957.pdf
Day 4 March 15 - (Equip IOPs) Equipment and Incorrect Operations
1 Action - Cdn Gas Leaks
- 1 Action - Equip IOPs NEB Response - Canadian Gas Leaks.pdf
- Gas Release-Leak (Canada) 2007-2012Chart Q4 r1.xls
10 Obs - TEP Additions
- 10 Observation Equip IOPs - NEB Response - Threat References.pdf
11 Obs - Program specific risk assessment
- 11 Observation Equip IOPs - NEB Response - Risk Assessment.pdf
2 Action - Annual report
- 2 Action Equip IOPs - NEB Response - Annual Summary.pdf
- 2013 Valve WIG KPIs.pdf
- Valve Issues and Actions Summary2012.pdf
3 Action - Monthly management review
- 3 Action Equip IOPs - NEB Response - Monthly Management Review.pdf
- Engineering and Asset Reliability October 2012 Business Review filed (in data room)
Day 4 March 15 - (FPIPE) Facility Piping
1 Action - Annual report
- 2012 PMP Annual Report FPIPE (CDN) Final (in data room)
2 Action - 9 Obs - Past station piping program
- 2 Action FPIPE - NEB Response - Previous Process.pdf
- 2003.04.TEP-CP-DT Cathodic Protection Diagn.PDF
- 2004.03.25 TES-CP-CR.pdf
- 2005.07.07 TES-CP-SS Cathodic Protection Survey Spec.pdf
- 2008.12.21 Fugitive Emissions Inspection.doc
- 2009.01.07 Relief Valve Inspection and Overhaul Program.doc
- 2009.06.25 Excavation Procedure (Canada and Mexico).doc
- 2009.06.29 Facilities Integrity Inspections.doc
- 2009.07.24 Meter Station General Maintenance Gas Transmission.doc
- 2009.07.29 Valve and Valve Operator Inspection and Servicing.doc
- 2009.07.30 Valve and Valve Operator Leak Inspection and Cycle Test (Canada).DOC
- 2161986_PI2011 Edson Meter Station Sour Bottle Integrity Assessment and Permanent Drain Scoping.pdf
- A1-1206ST-80-L1-FG56_14.tif
- A1-1206ST-80-L1-FG78_12.tif
- AB Field Lake CS - 2011 Facility Pipe Assessment Report.pdf
- Action 2 FPIPE - NEB Response - Previous Process.pdf
- CP Annual Station Exception Report - Rideau Area.pdf
- CP Annual Station Exception Report - STN 1206 Deux Rivieres CS.pdf
- CP Annual Station Report - STN 1401 Iroquois CS.pdf
- CP Remedial Station 1206_IFC_Set.pdf
- Dec Sum AB Field Lake Compressor Station Piping Recoat 2011_March14.doc
- Facilities Integrity Work Orders Canada 2010.xls
- IIT Issue 172642.pdf
- IIT Issue 209400.pdf
- IIT Issue 228504.pdf
- IIT Issue 228656.pdf
- IIT Issue 228827.pdf
- IIT Issue 229998.pdf
- Measurement Routine M1-M12 2010 Canada.xls
- ML Maple Niagara Riser Program - 2012 Facility Pipe Assessment Report.pdf
- ML Quebec Riser Program - 2012 Facility Pipe Assessment Report.pdf
- ML Rideau Riser Program - 2012 Facility Pipe Assessment Report.pdf
- Motor Vehicle Operation Program.pdf
- Pipeline Inspection Report - Torrington CS - Sep 11 2012.doc
- Snow Removal Procedures.doc
- TES-COAT-EPU External Multi-Component Liquid Coating Systems for Below Ground Facilities (Cdn-US-Mex).pdf
- TES-COAT-P1 Paint Systems for Above Ground Facilities (Non-Coastal) (Cdn-US-Mex).pdf
- TQM Riser Program - 2012 Facility Pipe Assessment Report.pdf
2 Obs - New Program Implementation
- 2 Observation FPIPE - NEB Response - New TEP.pdf
- Integrity Management Process for Pipelines Rev 2.0 3892900.pdf
3 Obs - Station piping body leaks
- 3 Observation FPIPE - NEB Response - Pipe Body Leaks.pdf
6 Obs - Class locations and consequences
- 6 Observation FPIPE - NEB Response - Class Locations and Consequences.pdf
- TEP-INT-PR Pipe Integrity Process Review Procedure 006522487.pdf
- TEP-INT-PRIME Risk Assessment Using PRIME 003972569.pdf
- TEP-ITM-FPIPE-CDN Facility Pipe Integrity Management Program 007379193.pdf
Day 5 March 19 - (MECH) Mechanical Damage and Public Awareness
1 Action - Excavation Checklist
- 1 Action MECH - NEB Response - Excavation Checklist.pdf
- Action1_Completed Excavation Checklist.pdf
2 Action - Excavation to threat managers
- 2 Action MECH - NEB Response - Interaction of Threats for Planned Excavations.pdf
- Calnash Trucking Crossing email.pdf
- PI 2009 SI Project Dec Summary- AB-Simonette River Crossing-Monitoring Equipment Installation and Corrosion 3776714.pdf
- RE D-8994-1, Calnash Trucking - Corrosion response.pdf
- RE D-8994-1, Calnash Trucking - Geotech response.pdf
- RE D-8994-1, Calnash Trucking - SCC Response.pdf
- TEP-ITM-ECOR-CDN External Corrosion Threat Management Program.pdf
3 Action - Excavation life cycles
- 3 Action MECH - NEB Response - Excavation Lifecycle Examples.pdf
- EX1_Email_Correspondence_MLV 19-20-3 Safe Dig Pressures.htm
- EX1_Engineering_Evaluation_Safe Dig Pressure MLV 19-20-3.pdf
- EX1_Excavation Procedure Checklist.pdf
- EX1_Field Integrity Report.pdf
- EX1_PulDown_ Compressor Elog Entry (19-20-3)-2.pdf
- EX1_PullDown_Compressor Elog Entry2 (19-20-3).pdf
- EX1_Stake Out Report.pdf
- EX2_Excavation Check List - SMS Line.pdf
- EX2_FW Longlac Lateral Safe Dig Pressure.htm
- EX2_Integrity Field Report.pdf
- EX2_Locate Request.docx
- EX2_Longlac email Ops to Field and Gas Control.pdf
- EX2_Longlac excavation Gas Control Logs.pdf
- EX2_One Call Ticket.pdf
- EX2_Safe Excavation Pressure Engineering Evaluation.pdf
- EX2_Stake Out Report.pdf
- EX3_3RD_ Party_PipeLine_Inspection_Report.pdf
- EX3_3RD_Party_Crossing_Agreement.pdf
- EX3_3RD_Party_Crossing_AsBuilt.pdf
- EX3_3RD_Party_OneCall.pdf
- EX3_3RD_Party_StakeOut_Report.pdf
- FW SCADANET DATA TRENDING DATABASE.msg
- MLV 19-20 Line 100-3 Isolation Procedure.pdf
4 Action - Mechanical Damage Committee 2011 Annual Review
- 4 Action Mechanical Damage - NEB Response - Excavation Steering Committee.pdf
- Excavation Report - March 2013.pdf
- Excavation Steering Committee Meeting Minutes.pdf
- Excavation with Spoon Attachment - April 2008 4846083.pdf
- Ground Disturbance Excavation Requirements - January 2008 4784248.pdf
- TES-PROJ-OHP Powerline Specification_IFR.pdf
- TOP Excavation Procedure 3672343.pdf
- TOP Overhead Powerline Procedure IFR.pdf
5 Action - Pressure Reduction Request
- 5 Action MECH - NEB Response - Safe Dig Pressure.pdf
- Document 1_Derate Calculation Request_Email.pdf
- Document 2_Engineering_Evaluation_Safe Dig Pressure .pdf
- Document 3_Isolation Procedure.pdf
- Document 4_ Compressor Elog Entry (19-20-3)-2.pdf
- Document 5_Compressor_Elog Entry2 (19-20-3).pdf
6 Action - Regional Public Awareness Programs
- 2012 Eastern Region Approved IPA Regional Overview Plan.pdf
- 2012 RMR IPA Regional Plan FINAL.PDF
- 6 Action MECH - NEB Response - Regional Public Awareness Programs.pdf
- IPA Regional Plan Overview NOR_MAR2_2012_FINAL.PDF
- IPA Regional Plan Overview Wildrose.pdf
- PA Regional Plan Overview (Central Region)2012 Final.pdf
9 Obs - Depth of Cover Surveys
- 2012 12 03 NEB Agricultural Crossing Consultation.pdf
- 9 Observation MECH - NEB Response - Depth of Cover Surveys.pdf
- NEB_Exemption_Order_MO-21-2010.pdf
- OB9_Aerial Patrol Reported_DOC_IIT233782.pdf
- OB9_Integrity Field Report.pdf
- OB9_Landowner Reported_DOC_IIT230784.pdf
- OB9_Pipeline Inspection Report.pdf
10 Obs - Safe Operating Pressure
- 10 Observation MECH - NEB Response - Safe Operating Pressure.pdf
- TOP Maximum Pressure Pipelines with Known or Suspected Integrity Concerns Canada 3671945.pdf
- TOP Pipeline Defect Assessment and Repair Procedures Canada 3674615.pdf
Day 5 March 19 - Complainant Allegations
1 Add Issue - Fittings Components Procurement Specifications
- 1 Add Issue - NEB Response - Fittings Components procurement Specs.pdf
1a Issue - Non-Independent Inspections
- 1a Issue - NEB Response - Non-Independent Inspections.pdf
- TEP-NDT-ADT Procedure for Non-Destructive Examination (NDE) Audits 3797402.pdf
1b Issue - Welding Inspections
- 1b Issue - NEB Response - Welding Inspections.pdf
- Edson Extension Hydro Test-Visual and Weld Parameter Record Overview.pdf
- Edson Ext-Weld Parameter Records.pdf
- Edson VT Reports.pdf
- Edson-Daily Inspection Reports.pdf
2 Add Issue - Reporting of Non-Compliances
- 2 Add Action - NEB Response - Reporting of Nonconformances.pdf
- Code of Business Ethics Policy.pdf
- Ethics and Compliance Organization.pdf
- Ethics and Compliance.pdf
- Ethics Help Line.pdf
- FAQ.pdf
- List of compliance coordinators by department.pdf
- Raising A Concern.pdf
- TransCanada Code of Business Ethics.pdf
3 Add Issue - NonCompliance Reporting
- 3 Add Issue - NEB Response - Non-Compliance Procedure Reporting.pdf
- TEP-NDT-VT Visual Examination 7381161.pdf
4 Issue - Non POE sign off follow up
- 5 Action - NEB Response - Non POE Sign off.pdf
- TES-ENG-POE Practice of Engineering 3672108.pdf
5 Issue - Transitions and Joining
- 6 Issue - NEB Response - Transitions and Joining.pdf
- TEP-MECH-TRAN Selection of Transition Pieces and Joining Methods 6256.pdf
6 Issue - AUT Criteria
- 7 Issue - NEB Response - AUT Criteria.pdf
- TES-NDT-UT1 Mechanized Ultrasonic Examination of Pipeline Girth Welds 3670963.pdf
7 Issue - NDE Audit Procedure
- 9 Issue - NEB Response - NDE Audit Procedure.pdf
- TEP-NDT-ADT Procedure for Non-Destructive Examination (NDE) Audits 3797402.pdf
Day 6 March 20 - OPP
01 Action - Pressure Control and OPP Procedure
- 1 Action OPP - NEB Response - Over Pressure Protection.pdf
- Evidence 1_IIT 240971 Information.pdf
- Evidence 10 IIT 241921 Technical Memo Lifting derate.pdf
- Evidence 11 IIT 241924 - SCADA Pressure Data.xls
- Evidence 12 IIT 241924 Elog Entries.doc
- Evidence 13 IIT 241924 Facility Notepad.pdf
- Evidence 2_IIT 240971 Technical memo_Derate.pdf
- Evidence 3_IIT 240971 Technical memo Lifting derate.pdf
- Evidence 4 IIT 240971 - SCADA Pressure Data.xls
- Evidence 5 IIT 240971 Elog Entries.doc
- Evidence 6 IIT 240971 Facility Notepad.pdf
- Evidence 7 IIT 240971 Isolation Procedure.pdf
- Evidence 8 IIT 241924 Information.pdf
- Evidence 9 IIT 241924 Technical Memo Derate.pdf
02 Action - Meter Station OPP Plan
- 2 Action 8 Observations OPP - NEB Response - Meter Station Over Pressure Protection.pdf
- TEF-OPP-VER-S-OFF-CDN Customer OPP Systems for New Meter Stations - TransCanada Sign-Off Form 7772654.pdf
- TEF-VER-OPP-RFI-CDN Customer OPP Systems for New Receipt Meter Stations - Request for Information Form 6587713.pdf
Day 6 March 20 - Pressure Vessels
01 Action - Qualification req for Examiner
- 1 Action Pressure Vessel - NEB Response - Examiner Qualifications.pdf
- Pressure Vessel Attachment 1: Vendor Qualification.pdf
- Pressure Vessel Attachment 2: Internal training.pdf
02 Action - 29C pressure vessel Comm
- Action 2 Pressure Vessel - NEB Response - -29C Pressure Vessel.pdf
Day 6 March 2010 - Tanks
01 Action - low pressure piping integrity program
- 1 Action Tanks - NEB Response - Low Pressure Piping rev 01.pdf
04 Obs - Inventory
- 4 Observation Tanks - NEB Response - Underground tank inventory.pdf
07 Obs - Ground Tank Inspection
- 7 Observation Tanks - NEB Response - Tank Inspection Audit.pdf
Day 6 March 20 - Valves for OPP and Pressure Control
01 Action - Leaking Valve Process and List
- 1 Action Valves for OPP - NEB Response - Leaking Valve Process and List.pdf
- TOP Gate Valve Position Inspection 6493970.pdf
- TOP Gate Valve Position Inspection Form 6598306.pdf
- TOP Pipeline Operations Gas Handling 3672508.pdf
01 Add Action - Sour Service Response
- 1 Add Action Valves for OPP - NEB Response - Sour Service Response.pdf
Day 7 April 2 - (CA-PA) Corrective and Preventive Actions
- 2 Action Day 8 CA-PA - TransCanada Corrective and Preventive Actions DRAFT April 5 2013.pdf
- TEP-ILI-DEF-CDN Analysis of Deformation In-Line Inspection Data 006980190.pdf
- TOP Aerial Pipeline Patrol 3672387.pdf
- TOP Pressure Control of Leaking Pipelines 3841207.pdf
- TransCanada Oil Pipelines Unit Start-Stop Procedure 6813148.pdf
Day 7 April 2 - WOF Water Crossings
- 1-4 Action Day 7 WOF - NEB Response - Water Crossings.pdf
- B-18b_-_Keystone_Responses_to_NEB_IR_3_(A0Y4Q8)_.pdf
- Consolidated Valve and Geotech Water Crossing Listing.xls
Day 8 April 3 - Corrective and Preventive Actions
- 5 Action -Day 8 CA-PA - NEB Response - Significant SCC.pdf
- NEB Notification Significant SCC NPS30 MLV 115-116 and NPS20 MLV 130-139 Line 100-1 March 22 2012.pdf
Day 8 April 3 - Leaking Dents
- 1 Action Day 8 - NEB Response - Leaking Dent.pdf
Day 8 April 3 - Liquid Sour Service and H2S Tests
- 2 and 3 Actions Day 8 - NEB Response - Liquid Sour Service and H2S Tests.pdf
- Gibson MSDS Petroleum Crude Oil 2008 12 31.pdf
- TOP API 653 Aboveground Storage Tank Inspection 7167240.pdf
- TOP Portable Gas Detection of the Atmosphere 3835957.pdf
- 2008 Assay report for Surmont Heavy Blend (SHB).xls (in data room)
- Commodity Approval Form for their Access Western Blend (AWB).pdf (in data room)
- Commodity Approval Form for their Peace Heavy (PH assay).pdf (in data room)
Day 8 April 3 - List of Upcoming Excavations
- 2013 ML TQM Risers Program - Site List NEB Visit.xls
- 4 Action Day 8 Excavation-Inspection Schedule April May 2013.pdf
Day 8 Post Meeting - Potential for SCC
- Post Meeting Day 8 - NEB Response - Potential for SCC.pdf
Additional Documents Requested
- Natural Gas Leak Detection Procedure Canada, EDMS No. 003676669
- TEP-INT-LEAK Pipe Integrity Leak Detection and Evaluation, EDMS No. 007379105
- Pressure Control of Leaking Pipelines, EDMS No. 003841207
- 2013-07-25 Response to NEB Audit Questions June 14 2013.pdf
2013-09-08 Response to NEB Audit Questions
- 2013-08-15 Below Specification Facility Fittings Response.pdf
- CB2013-208-0075781_01-01R0 HTR-18597 Lakesend Pump Station.pdf
- CB2013-208-0075781_01-01R0 HTR-26056-01 Monitor Pump Station.pdf
- CB2013-208-0075781_01-01R0 U13508VOR Lakesend Elbows.pdf
- CB2013-208-0075781_01-01R0 U13509VOR Lakesend Tees.pdf
- CB2013-208-0075781_01-01R0 U-20130727-01HS.PDF
- Emc2 Keystone Fitting Report-for Canada.pdf
- Piping Stress Analysis Report - Cdn Pump Stn Fittings Analysis 8288118.pdf
- 9-8-2013_Response to NEB regarding Keystone Expanded Pipe.pdf
- Blade Energy Report_Keystone Coupon Mech and Metallurgical Testing.pdf
- Date modified: