In accordance with section 103 of the Canadian Energy Regulator Act, the Canada Energy Regulator (CER) conducted a compliance audit of the auditee. The focus of the audit was on Damage Prevention. The objective of this audit was to verify whether the auditee’s Damage Prevention program:
- is effectively integrated within the company’s management system as per section 6 of the Canadian Energy Regulator Onshore Pipeline Regulation
(SOR/99-294)(OPR); and - is able to anticipate, prevent, manage and mitigate damage to its pipeline as per section 47.2 of the OPR and section 16 of the Canadian Energy Regulator Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies
(SOR/2016-133).
The CER issued its Final Audit Report to the auditee on 19 September 2023. Since there were no issues of non-compliance noted during this audit, the auditee was not required to file a Corrective and Preventive Action (CAPA) Plan with the CER.
The CER now considers this audit to be closed. Note the auditee is accountable for maintaining compliance throughout the life cycle of its regulated facilities. The CER will verify ongoing compliance through future compliance verification activities.
If you require any further information or clarification, please contact , lead auditor, at , or at 1-800-899-1265.
Yours sincerely,
Signed by
Lead Auditor
cc: , Canada Energy Regulator, email
Regulatory Notifications, TC Energy, email ,
Canada Energy Regulator,
email ,
Canada Energy Regulator, email
- Date modified: